Southwest Wastewater Trunk Line

Capital2020_SWSewer

The Southwest Wastwater Trunk Line will provide needed wastewater system capacity for South College Place going from the Commercial Drive area, through Meadowbrook, Harvest Meadows, and the recently annexed property across from College Place High School. Wastewater will be conveyed west to the City's Wastewater Treatment Plant. A new lift station will be constructed on city-owned property on Teal Rd to replace a temporary, out-dated, at capacity lift station at the southeast corner of College Avenue and Lamperti Street. J-U-B Engineering with the assistance of PBS is completing final engineering plans for the project.This project will likely go out to bid in Summer 2020 with construction going from late Summer 2020 through Summer 2021. The estimated cost of the project is around $5.5 million dollars. 