SW SEWER PROJECT

June 14th, 2022: This project is substantially complete. Apollo will be doing a grind and overlay on South College Avenue between Cedar Bend and Mojonnier this Summer to fix some settling issues. The Public Notice and Detour Map are located here. 

February 16th, 2022 Project Update


December 1st, 2021 Project Update

October 1st, 2021 Project Update




Mid August 2021 Update



Late April 2021 Update


March 2021 Update



SW Sewer Map

Contacts
Public Works Director Mr. Robert McAndrews
Em: rmcandrews@cpwa.us
Ph: (509)-394-8526

Press Release - S College Ave Temporary Closure (7-13-2021)
Press Release - SW Mojonnier Rd Temporary Closure (5-10-2021)

The Southwest Wastewater Trunk Line will provide needed wastewater system capacity for South College Place going from the Commercial Drive area, through Meadowbrook, Harvest Meadows, and the recently annexed property across from College Place High School. Wastewater will be conveyed west to the City's Wastewater Treatment Plant. A new lift station will be constructed on city-owned property on Teal Rd to replace a temporary, outdated, at capacity lift station at the southeast corner of College Avenue and Lamperti Street. J-U-B Engineering with the assistance of PBS is completing final engineering plans for the project. This project has appeared in the city's six-year Capital Facility Plan since 2018. It is financed through a combination of USDA-Rural Development Grant and Loan Dollars, State Department of Ecology Grant/Loan Dollars, Port .09 Grant, and Wastewater Utility Funds. The estimated cost of the project is around $7.5 million dollars. 

Legislative Gateway
Doc app

Document Center

The Document Center provides easy access to public documents. Click on one of the categories below to see related documents or use the search function.

Categories always sorted by seq (sub-categories sorted within each category)
Documents sorted by SEQ in Ascending Order within category

Legal Documents6 documents

  • Resolution: 19-008 SW Sewer Engineering
    document seq 0.00
    This document governs the relationship between the City and property owners surrounding the engineering phase of the project.
  • Resolution 20-050: SW Sewer Construction Phase
    document seq 0.00
    This is the Memorandum of Understanding between the City and property owners pertaining to construction phase of the SW Sewer project.
  • Resolution 19-035: Konen Property Acquisition
    document seq 0.00
    Acquisition of five acres for wastewater lift station on SW Teal Rd.
  • Easement Document: McKeirnan's
    document seq 0.00
    This document governs the permanent easement for the Southwest Wastewater Trunk Line.
  • Easement Document: Christianson
    document seq 0.00
    This document dedicates easement for the Southwest Wastewater Trunk Line from the Christianson's
  • SW Sewer Lift Station Property Appraisal
    document seq 0.00
    Appraisal for Five Acres Needed for Lift Station

Grant Documents6 documents

  • SW Sewer Financing Document
    document seq 0.00
    Document detailing financing for the Southwest Wastewater Trunk Line
  • Department of Ecology: Signed Acknowledgement Form
    document seq 0.00
    Signed form to begin work to accept grant/loan
  • USDA-RD: Grant Document
    document seq 0.00
    USDA-RD Grant Document
  • Resolution 20-017: USDA-RD Intent to File
    document seq 0.00
    Intent to File USDA-RD Grant Resolution
  • Port of Walla Walla: .09 Sales Tax Grant Agreement
    document seq 0.00
    Grant Agreement for SW Sewer
  • Department of Ecology: Grant & Loan Agreement
    document seq 0.00

Engineering3 documents

  • Southwest Sewer Facility Plan
    document seq 0.00
    This document is the Southwest Sewer Facility Plan Addendum to the City's Wastewater System Plan
  • SW Sewer SEPA Document
    document seq 0.00
    This is the SEPA document for the Southwest Wastewater Trunk Line
  • Southwest Wastewater Trunk Line: Updated Alignment College Ave Corridor (Oct 2020)
    document seq 0.00
    Updated engineering alignment through College Avenue.

Construction2 documents

  • Construction Contract with Apollo Inc (1-12-2021)
    document seq 0.00
    Construction Contract with Apollo Inc.
  • SW Sewer Construction Schedule: February 26th, 2021
    document seq 0.00
    Draft Construction Schedule put together by J-U-B Engineers and Apollo Inc as of February 26th, 2021