Public Works Director Paul Hartwig
Em: phartwig@cpwa.us
Ph: (509)-394-8526
Update: Central Washington/Shamrock Asphalt has completed pouring asphalt. Striping will occur on Friday, April 16th. Project will close out week of April 19th, 2021. (4-15-2021)
The City of College Place received a grant for over $287,000 to resurface Meadowbrook Blvd from State Route 125 to Lamperti Street. This project will include a new asphalt surface, fix broken sidewalk panels, and some traffic reconfiguration work at the south partial entrance to Wal-Mart. The engineering work was conducted in Spring 2020. Construction was delayed due to a freeze put on Capital Projects not underway through State Transportation Improvement Board due to funding shortfalls from COVID-19. The freeze was released in December 2020. The construction bid will be awarded in January 2021. The project should wrap up by Summer 2021.
Legislative Pathway
- City Council Meeting: July 23rd, 2019 Authorization to Pursue Grant
- City Council Meeting: December 19th, 2019 Transportation Improvement Board Grant Agreement
- City Council Meeting: January 28th, 2020 Authorization to Contract with Anderson Perry Engineers

Document Center
The Document Center provides easy access to public documents. Click on one of the categories below to see related documents or use the search function.
Search for file type:
Categories always sorted by seq (sub-categories sorted within each category)
Documents sorted by SEQ in Ascending Order within category
Documents sorted by SEQ in Ascending Order within category
Please click on one of the categories below to see uploaded documents.
CAT:534
file:537
file:538
CAT:535
file:539
CAT:536
Construction Engineering Contract with Anderson Perry
file:611
Construction contract with Central Washington Asphalt.
file:612