March 14th, 2022: Nelson Corp has mobilized to the site and is starting to construct the well house and order the appropriate wellhouse machinery. It is expected this project will be substantially complete by the end of Summer 2022.
Mid August 2021 Update
April 2021 Update
Late Fall 2021 Update
Contact
Public Works Director Robert McAndrews
Em: rmcandrews@cpwa.us
Ph: (509)-394-8526
This project replaces drinking water well #2 and is now known as Well #6. Drinking Water Well #2 experienced severe well shaft/geological issues and through an assessment by Keller Engineering it was determined that it needed to be replaced. The City successfully lobbied for financial assistance in the form of a Legislative Appropriation and a State Department of Health Drinking Water Revolving Fund Grant & Loan. The engineering team is charged with designing the well, well house, and associated mechanical equipment is RH2 Engineering/Keller Engineering. Schneider Well Drilling drilled the well shaft to a depth of 800 feet. Initial pump tests have indicated it has the ability to pump up to 5,000 gallons per minute. The engineering team is now working on final engineering for the well house and mechanical equipment. The engineering should wrap up by Fall 2021. The well house and mechanical equipment will be constructed throughout Late 2021/Early 2022. The City is aiming to have the well online by Spring 2022.
Legislative Pathway
- City Council: July 11th, 2017 Well No. 2. Relocation Update
- City Council: August 22nd, 2017 Well No. 2. Design Contract
- City Council: September 12th, 2017 Water Bond Ordinance
- City Council: November 28th, 2017 DWSRF Well No. 2 Relocation Application Approval.
- City Council: February 28th, 2018 Well No. 2. Relocation Design Contract
- City Council: July 24th, 2018 DWSRF Well No. 2. Funding Applications
- City Council Workshop: August 7th, 2018 Well #2 Replacement Project Update
- City Council: October 23rd, 2018RH2 Contract Amendment for Well No. 2 Relocation SCADA Master Plan
- City Council Workshop: December 4th, 2018 IGA for Solar Array at Well No. 2.
- City Council Workshop: April 2nd, 2019 Update on City Well #2 Replacement
- City Council: April 9th, 2019 Well Drilling Contract with Schneider Equipment
- City Council: August 13th, 2019 Pacific Power Blue Sky Grant for Solar Array
- City Council: November 12th, 2019 Well No. 2 DWSRF Supplemental Loan/Grant Applications
- City Council Workshop: January 7th, 2020 Update on Well No 2/6
- City Council: January 28th, 2020 Supplemental Request Test Well Drilling Contract
- City Council: February 11th, 2020 Acceptance of Blue Sky Grant for Solar Array
- City Council Workshop: May 5th, 2020 Update on Well #2/6
- City Council Workshop: August 4th, 2020 Update on Well Projects
- City Council: August 11th, 2020 Supplemental DWSRF Agreement
- City Council Workshop: February 2nd, 2021 Well #6 Update
- City Council: August 10th, 2021 Well #6 Update
- Utilities & Transportation Advisory Commission: August 19th, 2021 Project Update
- City Council Workshop: September 7th, 2021 Key Project Drilldowns
- City Council: September 28th, 2021 Capital Facility Plan
- City Council: October 26th, 2021 Wellhouse Construction & Engineering Award
- Utilities & Transportation Advisory Commission: November 8th, 2021 FY 2022 to FY 2027 CFP

Document Center
The Document Center provides easy access to public documents. Click on one of the categories below to see related documents or use the search function.
Search for file type:
Categories always sorted by seq (sub-categories sorted within each category)
Documents sorted by SEQ in Ascending Order within category
Documents sorted by SEQ in Ascending Order within category
Please click on one of the categories below to see uploaded documents.
CAT:592
2018 Legislative Appropriation Contract through State Department of Commerce
file:595
Resolution 19-052 allowing Execution of DWSRF Grant & Loan Dollars
file:596
State Drinking Water Revolving Fund Loan for Well #6
file:597
CAT:593
file:598
file:599
file:601
CAT:594
file:600
file:722